Partners from Clackamas County to Portland are working together to bring TriMet's FX® (Frequent Express) service along 82nd Avenue from Clackamas Town Center to Portland’s Cully neighborhood. FX service will improve travel times and access to transit while providing better connections to jobs, schools, retail centers and other destinations along the route.
This transit project is coordinated with a community-led equitable development strategy for the area to support business and community stabilization and enhancement.
Timeline
- Planning: 2022-25
- Project steering committee recommended the locally preferred alternative (LPA) in January 2025
- Local and regional governments approve locally preferred alternative and adopt into transportation plans
- Design and environmental analysis: 2024-27 (projected)
- Project design and engineering
- Complete the National Environmental Policy Act (NEPA) process
- Pursue Federal Transit Administration Capital Investment Grant and other necessary funding
- Construction: 2027-29 (projected)
- Opening year: 2029-30 (projected)